Guidance on approach to applications for an adjournment and applications for an extension of time due to the Covid-19 pandemic

April 24, 2020

Guidance on approach to applications for an adjournment and applications for an extension of time due to the Covid-19 pandemic: Muncipio De Mariana & Others v (1) BHP Group Plc (7) BHP Group Ltd [2020] EWHC 928 (TCC):

On 20 April 2020, HHJ Eyre QC has given useful guidance on the approach to applications for an adjournment and applications for an extension of time due to the Covid-19 pandemic.

It will be noted that applications will not be granted automatically. The Courts are expecting greater use of technology and remote hearings, and there is an expectation that lawyers and other professionals will go further than previously expected in an effort to keep the wheels of justice turning.

Any application for an adjournment or an extension of time because of Covid-19 should have regard to the following.

Approach to applications to adjourn because of Covid-19

  1. The starting point as always is the overriding objective with the requirement that cases are to be dealt with justly; in ways which are proportionate to the amounts involved, the importance of the case, and the complexity of the issues; and expeditiously and fairly.
  2. In the current circumstances regard is also to be had to PD51ZA paragraph 4 which provides that:

“In so far as compatible with the proper administration of justice, the court will take into account the impact of the Covid-19 pandemic when considering applications for the extension of time for compliance with directions, the adjournment of hearings, and applications for relief from sanctions.”

  1. … I have concluded that the following principles govern the question of whether a particular hearing should be adjourned if the case cannot be heard face to face or whether instead there should be a remote hearing.
  2. i)  Regard must be had to the importance of the continued administration of justice. Justice delayed is justice denied even when the delay results from a response to the currently prevailing circumstances.
  3. ii)  There is to be a recognition of the extent to which disputes can in fact be resolved fairly by way of remote hearings.

iii)  The courts must be prepared to hold remote hearings in circumstances where such a move would have been inconceivable only a matter of weeks ago.

  1. iv)  There is to be rigorous examination of the possibility of a remote hearing and of the ways in which such a hearing could be achieved consistent with justice before the court should accept that a just determination cannot be achieved in such a hearing.
  2. v)  Inevitably the question of whether there can be a fair resolution is possible by way of a remote hearing will be case-specific. A multiplicity of factors will come into play and the issue of whether and if so to what extent live evidence and cross-examination will be necessary is likely to be important in many cases. There will be cases where the court cannot be satisfied that a fair resolution can be achieved by way of a remote hearing.

Approach to applications for an extension of time because of Covid-19

  1. In my judgment the approach to applications for the extension of time in the context of the Covid-19 pandemic is to be determined by having regard to the overriding objective; paragraph 4 of PD51ZA; and the protocols and guidance which have been referred to above. In addition regard is to be had to the approach to the adjournment of trials set out above. In the light of that the Defendants’ application is to be assessed against the following principles.
  2. i)  The objective if it is achievable must be to be keep to existing deadlines and where that is not realistically possible to permit the minimum extension of time which is realistically practicable. The prompt administration of justice and compliance with court orders remain of great importance even in circumstances of a pandemic.
  3. ii)  The court can expect legal professionals to make appropriate use of modern technology. Just as the courts are accepting that hearings can properly be heard remotely in circumstances where this would have been dismissed out of hand only a few weeks ago so the court can expect legal professionals to use methods of remote working and of remote contact with witnesses and others.

iii)  While recognising the real difficulties caused by the pandemic and by the restrictions imposed to meet it the court can expect legal professionals to seek to rise to that challenge. Lawyers can be expected to go further than they might otherwise be expected to go in normal circumstances and particularly is this so where there is a deadline to be met (and even more so when failing to meet the deadline will jeopardise a trial date). So the court can expect and require from lawyers a degree of readiness to put up with inconveniences; to use imaginative and innovative methods of working; and to acquire the new skills needed for the effective use of remote technology. As I have already noted metaphors may not be particularly helpful but the court can expect those involved to roll up their sleeves or to go the extra mile to address the problems encountered in the current circumstances. It is not enough for those involved simply to throw up their hands and to say that because there are difficulties deadlines cannot be kept.

  1. iv)  The approach which is required of lawyers can also be expected from those expert witnesses who are themselves professionals. However, rather different considerations are likely to apply where the persons who will need to take particular measures are private individuals falling outside those categories.
  2. v)  The court should be willing to accept evidence and other material which is rather less polished and focused than would otherwise be required if that is necessary to achieve the timely production of the material.
  3. vi)  However, the court must also take account of the realities of the position and while requiring lawyers and other professionals to press forward care must be taken to avoid requiring compliance with deadlines which are not achievable even with proper effort.

vii)  It is in the light of that preceding factor that the court must be conscious that it is likely to take longer and require more work to achieve a particular result (such as the production of evidence) by remote working than would be possible by more traditional methods. In the context of the present case the Defendants said that meetings conducted remotely took twice as long and achieved less than those conducted face to face. The Claimants challenged the precise calculation but accepted that such meetings would be likely to take longer and that is readily understandable particularly in a case such as the present involving large quantities of documents and requiring at least to some extent the use of interpreters.

viii)  In the same way the court must have regard to the consequences of the restrictions on movement and the steps by way of working from home which have been taken to address the pandemic. In current

  1. ix) Those factors are to be considered against the general position that an extension of time which requires the loss of a trial date has much more significance and will be granted much less readily than an extension of time which does not have that effect. That remains the position in the current circumstances and before acceding to an application for an extension of time which would cause the loss of a trial date the court must be confident that there is no alternative which is compatible with dealing fairly with the case.

If you need assistance with applying for adjournments or extensions of time please contact us.

 

Justin Perring

 

jperring@pallantchambers.co.uk

 

Tags: Civil litigation

 

Disclaimer: this post is provided free of charge and if for information purposes only. It does not give legal advice and should not be relied on in respect of the same. No liability is accepted for the accuracy or correctness of the post, or for the consequence of relying on it by any member of Chambers or Chambers as a whole.